Resurfacing on K-14 and K-284 to begins today

Beginning today (Thursday), the Kansas Department of Transportation plans to begin a mill and overlay project on about 26 miles of K-14 and K-284 in Ellsworth and Lincoln counties.

Work on K-284 will occur from the west city limits of Barnard and continue west to the K-14/K-284 junction. Work on K-14 will occur from the K-14/I-70 junction and continue north to the Lincoln/Mitchell County line.

During construction, flaggers and a pilot car will be used to direct one lane of traffic through the work zone at a reduced speed. Drivers should be prepared for a delay of up to 15 minutes and plan extra time in their travel schedules.

APAC-Kansas Inc. of Hutchinson is the prime contractor for this $6.6 million project and has scheduled work to be completed by September, weather permitting.

 